Middle East Large Engineering Project — Formwork Plywood for Rapid Construction
JINDIWOOD Partners with Saudi Contractor: Phenolic Film Faced Formwork Achieves 28 Reuses for NEOM
Project Overview
| Item | Content |
|---|---|
| Client | XX Construction (major Saudi engineering contractor) |
| Location | NEOM, Saudi Arabia |
| Project Type | Formwork supply for infrastructure construction |
| Core Material | Phenolic film faced formwork plywood (18 mm, 1220 × 2440 mm) |
| Key Requirements | Reuses ≥25, surface flatness ≤0.5 mm/2 m, first 20 containers delivered within 90 days |
| Cooperation Results | First batch achieved 28 reuses, client added 30 containers, total 80 containers, listed as qualified supplier |
I. Client Background
XX Construction is a major Saudi engineering contractor participating in the infrastructure construction of a zone in the new city NEOM. The project has a tight schedule and places extremely high demands on the reuse count and stability of formwork.
II. Challenges and Requirements
The client needed an order of 50 containers of phenolic film faced formwork plywood, with the following requirements:
1. High Reuse Count
Reuses ≥25
Formwork must remain stable under high-intensity construction, without delamination or separation
2. High Flatness
Surface flatness ≤0.5 mm/2 m
Ensure a flat and smooth concrete surface
3. Fast Delivery
The first 20 containers must arrive in Saudi Arabia within 90 days
The project schedule is tight; any delivery delay directly affects construction progress
III. JINDIWOOD Solutions
Addressing the client's high standards, JINDIWOOD provided a comprehensive solution from capacity coordination to technical assurance:
1. Three-Factory Coordination, Synchronized Production
Linyi Wanyuan Wood Industry, Linyi Zhongyi Board Industry, and Linyi Wanchi Board Processing Factory coordinate production
Synchronized production of this order, ensuring sufficient capacity and controllable delivery
Strict quality control to ensure consistent quality across every batch
2. High-Density Eucalyptus Core + Double-Sided Phenolic Film
High-density eucalyptus core enhances compressive strength and water resistance
Double-sided phenolic film ensures high reuse performance, wear resistance, and waterproofing
Adapts to the hot and dry Middle East climate, stable for long-term use
3. First Batch Produced in 25 Days, Direct Shipment from Qingdao to Saudi Arabia
The first batch is produced within 25 days
Direct shipment from Qingdao Port to Saudi Arabia, optimizing the logistics route
Full traceability ensures on-time arrival
4. Third-Party Test Reports, Transparent Quality
Each batch includes a third-party test report
Tests include boiling water test, bonding strength, surface wear resistance, etc.
Data is verifiable and traceable, giving the client clear visibility into quality
IV. Cooperation Results
1. First Batch Formwork Achieved 28 Reuses
The first batch of formwork achieved 28 reuses on site, exceeding client expectations
Stable performance, with no delamination or separation
2. Client Added 30 Containers
The client added 30 containers
Total cooperation reaches 80 containers, deepening the partnership
3. Listed as Qualified Supplier
JINDIWOOD was listed in the contractor's qualified supplier directory
Laying a solid foundation for future cooperation
4. Client Evaluation
"JINDIWOOD's formwork helped us catch up on the schedule."
—— Project Procurement Manager
V. Project Highlights
Three-Factory Coordination: Three major factories in Linyi produce in sync, sufficient capacity, controllable delivery
High Reuse: High-density eucalyptus core + double-sided phenolic film, achieving 28 reuses
Fast Delivery: First batch produced in 25 days, direct shipment from Qingdao to Saudi Arabia
Transparent Quality: Third-party test report per batch, verifiable boiling, bonding, and wear data
Frequently Asked Questions FAQ
Q1: What product did JINDIWOOD provide to the client?
A: JINDIWOOD provided phenolic film-faced formwork plywood (18 mm, 1220×2440 mm) for the infrastructure construction of NEOM New City in Saudi Arabia, featuring high rotation resistance, high flatness, and good adaptation to hot, dry climates.
Q2: What are the client's core requirements for the formwork?
A: The client requires rotation cycles ≥ 25, surface flatness ≤ 0.5 mm/2 m, and delivery of the first 20 containers to Saudi Arabia within 30 days. The panels must remain stable under high-intensity construction, without debonding or delamination, ensuring a flat and smooth concrete surface.
Q3: How does JINDIWOOD guarantee production capacity and delivery times?
A: JINDIWOOD coordinates the production of its three factories — Linyi Wanyuan Wood Industry, Linyi Zhongyi Board Industry, and Linyi Wanchi Panel Processing Factory — to produce this order in parallel, ensuring sufficient capacity and controlled delivery times. The first order is completed in 25 days and shipped directly from Qingdao to Saudi Arabia, with full tracking.
Q4: What technology is used in this formwork?
A: We use a high-density eucalyptus core + double-sided phenolic film. The high-density eucalyptus core improves the formwork's compressive strength and water resistance; the double-sided phenolic film ensures high rotation performance, abrasion and water resistance, adaptation to the hot, dry Middle Eastern climate, and reliable long-term stability.
Q5: How does JINDIWOOD ensure quality transparency?
A: Each batch comes with a third-party test report, covering tests such as boiling water test, bonding strength, and surface abrasion resistance. The data is verifiable and traceable, allowing the client to see the quality at a glance.
Q6: What were the results of this collaboration?
A: The first batch of formwork achieved 28 rotations on site, exceeding the client's expectations. The client added 30 containers, bringing the total cooperation volume to 80 containers. JINDIWOOD was listed on the contractor's qualified supplier list. The project procurement manager commented: "JINDIWOOD's formwork helped us make up for lost time."